Construction
Publié le
|
20/10/2026

Construction of 3 classrooms and 2 staff accommodation units – EPP Konankro

Problem/ Context

The Konankro State Primary School (EPP), situated in the Bodokro sub-prefecture in the Gbêkê region of Côte d’Ivoire, has around 120 pupils. Despite its vital role in the education of local children, the school requires additional facilities to improve learning conditions and meet the needs of its pupil population. The lack of sufficient classrooms limits the school’s ability to accommodate pupils in suitable conditions.

Furthermore, the shortage of suitable accommodation for teachers makes it more difficult for them to settle in the area and may jeopardise their long-term commitment to the school. In light of this situation, the construction of three additional classrooms and two staff flats is a pressing priority. The completion of these facilities would help to improve the school environment, facilitate the work of teachers and provide pupils with better conditions in which to learn and succeed.

Detailed project description

The project involves strengthening the infrastructure of the Konankro Primary School through the construction of three additional classrooms and two staff accommodation units for teachers.

The main objective is to

  • improve teaching and learning conditions,
  • increase the school’s capacity and
  • encourage teachers to remain in the locality in the long term.

The planned works include the construction and fitting out of three classrooms, as well as the provision of two functional staff accommodation units for teachers. This infrastructure will provide a school environment better suited to the needs of pupils and teaching staff.

The direct beneficiaries will be the school’s approximately 120 pupils and its teaching staff. Pupils’ parents and the wider Konankro community will also benefit from the positive impact of the project. Through this initiative, we are seeking Action For Africa’s support to contribute to the development of education in rural areas and to ensure that the children of Konankro have a school environment more conducive to their success.

Informations générales
Project applicant
KONE KAKOUMANI MATHIEU
Primary school teacher
Contacts
School name

EPP KONANKRO

Location (village, region)
KONANKRO
Project category

Construction

Required Materials and Equipment
Construction icone
Buildings to Be Constructed

3 additional classrooms
2 staff accommodation units
1 office and 1 multi-purpose hall

Construction icone
Installations scolaires

3 latrine blocks
1 school fence
1 electrical system
1 borehole or water pump

Construction icone
Equipment, Materials, and Furniture

90 desks and benches
10 items of office furniture
25 packs of teaching materials

Main needs

School construction,Extension: new classrooms,School facilities,School equipment

Target learners

120 new children

Coût du projet

Estimation to be done

Project status

Received

Les autres projets de construction

Retrouvez tous les projets en cours

School image description

King’s Glory currently serves 883 learners in Kamuli District, including vulnerable children from families that struggle to meet education needs. The existing learning space is not sufficient for the number of learners being served. Additional classrooms are needed to reduce pressure on the existing facilities and provide a safer and more suitable environment for teaching and learning.

‍

Project overview ->
School image description

Lack of school to that proposed area and student suffer to a long distance to reach for thier school, lack of infastructure that support school

‍

Project overview ->
School image description
  • Roof with holes in some places, allowing rainwater to seep through
  • Ceilings detached from their supports
  • A dining hall for the cafeteria
  • If possible, a CIE meter for the school
  • Need for tables and benches

‍