Construction of 3 new classrooms – Zaza School Complex

Rwanda
|
Zaza Sector

Problem/ Context

The school has many children and few classrooms, hence some classes have almost seventy students in one class. This leads to poor perfomance since the teacher cannot manage such big number. The total number of students is 1756.

Detailed project description

Foundations and Masonry (cement, sand,stones,bricks) = 40,050,000 RWF
Roof (Timber, Frame,Iron sheets) = 21,001,500RWF
skilled labour = 9,750,000RWF
Doors and Windows = 8,900,000RWF
Floor and Paint = 950,000RWF Desks = 23,000,000RWF
Electricity ( Cables lamps Sockets) = 150,000RWF
Total Amount in Rwandan Francs. 103,801,500.RWF in USD it is aproximately 70, 373 USD.
The main objective is to reduce overcrowding in some classes hence improving the school perfomance.

Informations générales
Project applicant
Evalyne Ndungwa Mutheu
Headteacher
Contacts
School name

Groupe Scolaire Zaza (GS Zaza B)

Location (village, region)
Zaza Sector
Project category

Construction

Required Materials and Equipment
Construction icone
Buildings to Be Constructed

3 new classrooms
1 multi-purpose hall
1 IT room

Construction icone
Installations scolaires

1 water borehole
1 electric and solar system

Construction icone
Equipment, Materials, and Furniture

150 desks and benches
10 office desks and chairs
30 packs of teaching materials
250 school kits

Main needs

School expansion : new classrooms

Target learners

100

Coût du projet

103,801,500.RWF is aproximately $70,373 USD

Project status

Received

School Photos

Les autres projets de construction

Retrouvez tous les projets en cours

School image description
  • Roof with holes in some places, allowing rainwater to seep through
  • Ceilings detached from their supports
  • A dining hall for the cafeteria
  • If possible, a CIE meter for the school
  • Need for tables and benches

‍

Project overview ->
School image description

The klapleu modern middle school is a school established in a rural area. It is planned to operate on a two-track basis from sixth grade through ninth grade, which means a projected total of 8 classrooms. However, since its opening in 2025, there have been only 4 classrooms instead of the 8 planned. From 20 students at the start, there are now 173 students spread across 3 grade levels (6th, 5th, and 4th). The growing student enrollment. Therefore requires the construction and equipment of the remaining 4 classrooms.

‍

Project overview ->
School image description

The CRS school, founded in 1995, serves students from disadvantaged backgrounds. As a result, it faces many challenges that affect academic performance. In addition, the poor condition of the restrooms makes the children feel uncomfortable. Consequently, they relieve themselves outside the school.

‍

Project overview ->