Construction of 3 classrooms – Kab Gaye Primary School

Senegal
|
Kab Gaye

Problem/ Context

The pupils in the CI class are housed in a temporary shelter made of straw. There are 55 pupils in total, and they struggle to work properly given the circumstances. During break time, all the pupils go to the village square, which is about 400 metres from the school, to get their breakfast and often return late, hence the need for a school canteen.

Detailed project description

PROJECT TO BUILD A CLASSROOM AT KAB GAYE PRIMARY SCHOOL

Location: Kab Gaye, Kébémer
Department, Louga
Region, Senegal.

Beneficiary organisation: Kab Gaye Primary School.
Project leader: Headteacher.
‍

I. Background and rationale
Kab Gaye Primary School is a rural school situated in an area characterised by limited resources and significant needs for educational infrastructure.The school currently has 165 pupils spread across various classes and has four classrooms. However, inadequate infrastructure means the school has had to house the pupils in the Introductory Class (CI), which has 55 children, in a temporary shelter. This situation poses a major challenge to learning. Indeed, the precarious physical conditions affect the pupils’ concentration, their comfort and the quality of teaching and learning. Children starting their school career are particularly in need of a suitable, safe environment that is conducive to their development. Faced with this situation, the school wishes to engage technical and financial partners to build a permanent classroom for the CI pupils.

II. General objective: To improve the reception and learning conditions for pupils at Kab Gaye Primary School through the construction of a classroom suited to the needs of CI.

III pupils. Specific objectives: To replace the temporary shelter housing the 55 CI pupils with a permanent classroom. To provide pupils with a safe, comfortable learning environment conducive to concentration. To improve the teacher’s working conditions. To contribute to improving the quality of teaching and learning.

IV. Planned activities: Identification and approval of the site for construction. Preparation of the cost estimate and architectural plans.Construction of the classroom.Fitting out the classroom with desks, benches and educational furniture.Handover of the works and commissioning of the classroom.

V. Expected resultsA modern and functional classroom is built.The 55 CI pupils benefit from a suitable school environment. The teacher’s working conditions are improved. The pupils’ learning conditions and ability to concentrate are enhanced.

VI. Beneficiaries Direct beneficiaries: the 55 CI pupils and their teacher. Indirect beneficiaries: the 110 other pupils, teaching staff, parents and the Kab Gaye community.

VII. Support RequestedThe school is seeking support from partners to fund or fully construct the classroom, as well as to provide it with school furniture. The educational community remains willing to participate in local fundraising efforts and to facilitate the implementation of the project.

Informations générales
Project applicant
Ibrahima Philippe Diop
Directeur d'école
Contacts
School name

École élémentaire de kab gaye

Location (village, region)
Kab Gaye
Project category

Construction

Required Materials and Equipment
Construction icone
Buildings to Be Constructed

3 new classrooms
1 headteacher’s office
1 multi-purpose hall

‍

Renovation icone
Renovation and Restoration

Painting
Carpentry

‍

Construction icone
Installations scolaires

3 toilet blocks
1 electrical system
1 water borehole/pump

‍

Construction icone
Equipment, Materials, and Furniture

70 two-seater desks and benches
30 sets of teaching materials
20 chairs and office furniture

‍

‍

Main needs

Extension : nouvelles salles de classes,Équipements scolaires

Target learners

170

Coût du projet

To be done

Project status

Received

School Photos

Other construction projects

See all current projects

School image description

The klapleu modern middle school is a school established in a rural area. It is planned to operate on a two-track basis from sixth grade through ninth grade, which means a projected total of 8 classrooms. However, since its opening in 2025, there have been only 4 classrooms instead of the 8 planned. From 20 students at the start, there are now 173 students spread across 3 grade levels (6th, 5th, and 4th). The growing student enrollment. Therefore requires the construction and equipment of the remaining 4 classrooms.

‍

Project details ->
School image description

The CRS school, founded in 1995, serves students from disadvantaged backgrounds. As a result, it faces many challenges that affect academic performance. In addition, the poor condition of the restrooms makes the children feel uncomfortable. Consequently, they relieve themselves outside the school.

‍

Project details ->
School image description

For the past three years, we have been renting a room and space to house our preschool.
We started with 40 students and now have 80. We serve students in the younger, middle, and older preschool classes, as well as a special education class designed to support children who left public school at a very young age, as well as those facing learning challenges, to help them overcome them.
With our limited resources, we are struggling not only to build our own school but also to accommodate more students.

‍

Project details ->