Problem/ Context

ESTABLISHED in 2000. I have been running this school for three years now. But there are no amenities for these students. Under the previous principal, enrollment was at a maximum of 90 students. When I arrived, after giving the school a few coats of paint, I had 120 students in the first year, then 180, and 187 this year.

Detailed project description

We have 4 buildings, 3 classrooms, and a principal’s office, so we need to build 2 more classrooms. In 2024, we’ll have 180 students. Small tables and chairs: 100; swing set: none; playground equipment: none; restrooms without doors for either students or teachers; we need 2 restrooms for students and teachers.

Buildings to be renovated: 3 classrooms

-Painting, tiling, ceilings

-Electrical work in these rooms, plumbing, carpentry, cafeteria, playroom, and school supplies for underprivileged students.

These are the key needs. The immediate need that is most important to us is doors, tiling, and plastering for the 3 classrooms in time for the start of the school year. At the very least, the doors and tiling.

We are also requesting assistance with school supplies such as: mats, markers, slates, chalk, colored pencils, reams of paper, scissors, and all types of glue.

Project applicant
Mrs. NADIE ROSE BAGOU
School Director
+2250747688621
School name

Kennedy 2 Preschool in Daloa

Location (village, region)
Quartier Kennedy 2
Project category

Equipement

Main needs

Building renovation,Educational facilities

Target learners

200

Coût du projet

17 280 $ US Appr. 9 849 600 XOF

Project status

Received

List of needs
Construction icone
Buildings to Be Constructed

2 new classrooms
School cafeteria

Renovation icone
Renovation and Restoration

Painting and carpentry work
Tile and ceiling installation

Construction icone
Installations scolaires

4 Toilet blocks + Sinks

Construction icone
Equipment, Materials, and Furniture

100 small tables and chairs
Swings and playground equipment
School supply kits

School Photos

Toutes les autres écoles

Retrouvez toutes les candidatures transmises par les villages

Lack of school to that proposed area and student suffer to a long distance to reach for thier school, lack of infastructure that support school

Voir l'école
  • Roof with holes in some places, allowing rainwater to seep through
  • Ceilings detached from their supports
  • A dining hall for the cafeteria
  • If possible, a CIE meter for the school
  • Need for tables and benches

Voir l'école

The klapleu modern middle school is a school established in a rural area. It is planned to operate on a two-track basis from sixth grade through ninth grade, which means a projected total of 8 classrooms. However, since its opening in 2025, there have been only 4 classrooms instead of the 8 planned. From 20 students at the start, there are now 173 students spread across 3 grade levels (6th, 5th, and 4th). The growing student enrollment. Therefore requires the construction and equipment of the remaining 4 classrooms.

Voir l'école