The school originally planned (32 classrooms) was not fully completed due to a lack of funding. The current capacity (6 classrooms) is insufficient to meet the needs of the village and the surrounding areas.
The school has many children and few classrooms, hence some classes have almost seventy students in one class. This leads to poor perfomance since the teacher cannot manage such big number. The total number of students is 1756.

Foundations and Masonry (cement, sand,stones,bricks) = 40,050,000 RWF
Roof (Timber, Frame,Iron sheets) = 21,001,500RWF
skilled labour = 9,750,000RWF
Doors and Windows = 8,900,000RWF
Floor and Paint = 950,000RWF Desks = 23,000,000RWF
Electricity ( Cables lamps Sockets) = 150,000RWF
Total Amount in Rwandan Francs. 103,801,500.RWF in USD it is aproximately 70, 373 USD.
The main objective is to reduce overcrowding in some classes hence improving the school perfomance.
Groupe Scolaire Zaza (GS Zaza B)
Construction
3 new classrooms
1 multi-purpose hall
1 IT room
1 water borehole
1 electric and solar system
150 desks and benches
10 office desks and chairs
30 packs of teaching materials
250 school kits
School expansion : new classrooms
100
103,801,500.RWF is aproximately $70,373 USD
Received